We got the EECA notice and we know we need a Type II REM. What else started that day?

Most large plants that get the EECA 2024 notice know they need a Type II energy manager. Fewer notice that the audit clock started the same day, or how much work the REM has to do all year.

Rogowski current coils, voltage leads, insulated gloves and a safety helmet laid out before logging starts.
Field photo: our power logging kit, laid out before a measured audit.

The plant makes metal parts in the Klang Valley, and most of its energy goes into gas-fired furnaces. When the Energy Commission’s notice arrived, the engineering team knew what it meant. The site uses well over 50,000 GJ a year, so it needs a Type II Registered Energy Manager (REM). Their engineers hold Type I.

The plan was simple. Find a Type II, appoint them, register the appointment with the Commission.

That plan covers one of four deadlines. It also treats the REM as a name on a form, when the role is a year of work with personal fines attached to it. We have had the same conversation with several large plants this year, and the gaps are always in the same two places: the audit clock, and what the REM actually does.

Which clocks started with the notice?

A notice under s.3(3) of the Act starts two clocks on the day it is dated. The REM must be appointed within three months, and the first energy audit report must be submitted within one year. The REM’s appointment then starts two more: the energy management system must be developed within a year of it, and the first energy efficiency and conservation (EE&C) report is due 30 days after its first anniversary.

Deadline Counted from
Appoint the REM and notify the Commission: 3 months The notice
Submit the first energy audit report: 1 year The notice
Develop the energy management system: 1 year The REM appointment
Submit the first EE&C report: 30 days after 1 year The REM appointment

P.U.(A) 466/2024, reg. 4(2), 4(3) and 6(2); reg. 10(1)(a); reg. 8; reg. 9(a).

The mistake we see most often is reading the second row as if it ran from the REM appointment. Take a notice dated 1 March. The company spends three months finding a REM and appoints one at the end of May. The audit report is still due by 1 March the following year.

Timeline with example dates. A notice dated 1 March 2026 starts two clocks: appoint the REM by 1 June 2026, and submit the first energy audit report by 1 March 2027. The REM, appointed on 29 May 2026, starts two more: the energy management system by 29 May 2027, and the first EE&C report by 28 June 2027. That leaves about 9 months for the audit.
The four deadlines, with example dates. The audit clock runs from the notice, not from the REM appointment.

That leaves about nine months for a measured audit, and the audit guideline sets a floor. The main incomer must be logged for at least seven days over a full operating cycle, and the systems audited must make up at least 80% of the connected load. In practice, allow about a month from the purchase order before the auditor starts, then the fieldwork, then about a month for analysis and a report the company has time to read before it goes in.

P.U.(A) 466/2024, reg. 10(1)(a). GP/ST/No.49/2024 (Pind. 1/2026), para 4.1.10(b) and 4.1.12.

Which REM does the site need?

The type of REM depends on how much energy the site uses over any twelve consecutive months.

Energy use REM required
21,600 to 50,000 GJ Type I or Type II
Above 50,000 GJ Type II

The starting point is a REM from your own staff (reg. 4(1)). A site under 50,000 GJ can appoint its own Type I engineer, and some companies spend weeks looking for a Type II they do not need.

The Regulations also allow a REM from outside the company. That REM must be Type II, and the appointment can last no more than three years from the date of the notice (reg. 6(1)). When it ends, the company must appoint a REM from its own employees (reg. 6(4)). An external REM can serve up to seven other energy consumers at the same time (reg. 6(3)).

So an external REM is a bridge to your own. A Type I REM can apply to become Type II after a year as Type I with a valid practising certificate, once the Commission is satisfied with their knowledge of the Act and Regulations (reg. 14(2)). The plan that holds up is to appoint an external Type II now and use the three years to bring your own engineer up to Type II.

P.U.(A) 466/2024, reg. 4(1), 5, 6(1) to 6(4) and 14(2). On Suruhanjaya Tenaga’s public REM registers in July 2026 we counted 2,372 REMs, of whom 1,057 held Type II.

What does a REM actually do?

Most companies we meet expect to appoint the REM, register the appointment and move on. The Act lists the REM’s duties in s.5(2), and the Commission’s guideline spells them out. The REM must:

  • collect and analyse at least twelve consecutive months of energy data from before the appointment, then keep doing it for as long as the appointment lasts;
  • help the energy management committee prepare the energy policy and get top management to approve it;
  • propose the objectives, targets, action plans, resources and energy performance indicators, and get top management to approve the targets;
  • arrange at least four committee meetings a year and one management review with top management, with minutes recorded and endorsed;
  • check that the data is accurate and report on energy performance to the committee;
  • prepare the EE&C report and check its figures against the actual bills and invoices;
  • use the audit’s list of saving measures to propose an action plan, and propose how each saving will be measured and verified;
  • collect production data, an inventory of the equipment that uses the most energy, and the variables that move consumption, such as shutdown days.

Act 861, s.5(2). GP/ST/No.47/2024 (Pind. 1/2026), para 3(a) to 3(g).

The REM carries part of the risk personally. A REM who fails these duties, or fails to prepare the EE&C report, faces a fine of up to RM20,000 (s.5(4) and s.7(3)). The company’s own fines for missing the REM appointment, the energy management system or the reports go up to RM50,000. A careful REM will want to see the data, sit in the meetings and check the report before putting their name to it.

The four committee meetings and the management review are the minimum. The year’s work happens between them.

Can our own engineers start before the Type II arrives?

Yes. Most of the first quarter’s work is the company’s own duty, so your team can start this week. Developing and running the energy management system is the energy consumer’s duty under s.6(1). The guideline sets out the first steps: top management appoints a management representative, an energy management committee is formed, and the energy policy is drafted for top management to sign. A Type I engineer on a site above 50,000 GJ cannot be the appointed REM there, but they can lead this groundwork, and the appointed REM builds on it.

Act 861, s.6(1) and 6(2). GP/ST/No.46/2024 (Pind. 1/2026), paras 4.2 to 4.4.

The same goes for booking the audit. Appointing a Registered Energy Auditor is also the company’s duty (s.8(2)), and it does not have to wait for the REM.

How should we price an external REM?

Compare the fee with what it costs to employ a Type II engineer yourself: the salary, the employer’s contributions, the months it takes to recruit, and the risk that the engineer resigns. Then ask what the fee buys between the five meetings a year, and who does that work. We set out the five questions to ask before you sign in our piece on choosing an external REM.

What if there is no grant?

Many of the companies we speak to assume a grant will cover the audit. Plan as if it won’t. SEDA’s Energy Audit Conditional Grant is real, but it is limited and it comes with conditions. It can part-fund an audit of a site that uses 100,000 kWh of electricity a month or more, up to RM100,000 for industrial premises and RM60,000 for commercial buildings under the current RMK-13 terms. The 2026 implementation year had places for 52 commercial buildings and 56 industrial premises across the country. The company applies for it and receives it after the work, and it must then carry out the audit’s recommended measures, at a total cost at least equal to the grant, within 38 months of signing the Letter of Acceptance. SEDA has not yet announced the next cycle.

SEDA, Energy Audit Conditional Grant, Terms of Reference under RMK-13.

The deadlines do not wait for a grant. The REM is due in three months and the audit report in a year, whether a cycle opens or not. So the budget request should reach management in the first month, with two lines: the REM for the length of the appointment, and the audit. If a grant opens and the site qualifies, it lowers the net cost. Treat it as a bonus.

If you have not had a notice yet but think the site is near 21,600 GJ, put both lines into next year’s budget now. A notice that lands halfway through a financial year with nothing set aside is how an audit ends up squeezed into its last few months.

What should the first 90 days look like?

  1. In the first week, write down the date on the notice. Put the REM deadline and the audit report deadline in the diary now, and add the other two on the day the REM is appointed.
  2. In the same week, check which premises the notice names, and check the site’s energy use against the 50,000 GJ line so you know which type of REM it needs. The free threshold checker on eeca2024.my converts bills to GJ.
  3. Over the first four weeks, collect 24 to 36 months of bills for every form of energy the site buys, whether electricity, natural gas, LPG, steam, chilled water or biomass, with production output and operating hours for the same months.
  4. In the first month, send management a budget request with two lines, the REM and the audit, from your own funds. Count any grant as a bonus.
  5. Between weeks 2 and 6, name the management representative, form the energy committee and draft the energy policy. Your own engineers can lead this.
  6. By week 8, decide the REM route: your own Type II, your own Type I if the site is under 50,000 GJ, or an external Type II for up to three years with a named person to take over.
  7. By the end of month 3, appoint the REM and notify the Commission electronically.
  8. Within the first three months, appoint a Registered Energy Auditor and agree the measurement plan, working back from the audit report date.

What to take to your management

Two dates, one decision and a budget. The REM deadline and the audit report deadline, both counted from the notice. The REM route, with the name of the person who will hold the role in year four. And the cost of the REM and the audit, approved without waiting for a grant.

Where Innovast fits

Innovast Sdn Bhd is a Registered ESCO with Suruhanjaya Tenaga (ESCO 327(2023)/76/2024), with Registered Energy Auditors and Registered Energy Managers on staff. Our team has audited more than 60 facilities. For a site with a new notice, we provide an external Type II REM, from RM3,500 a month for quarterly attendance, with our team doing the data, the meeting papers and the EE&C report behind the REM. The same team can run the energy audit, so both clocks are planned together, and part of the service is getting your own engineer ready to take over.

Where a grant is open, we can help you apply, subject to availability, eligibility and terms and conditions. Our audit does not depend on it.

See the external REM serviceStart the EnMS with the free wizard

Revised Nov 2026 against Act 861, P.U.(A) 466/2024, GP/ST/No.46/2024, GP/ST/No.47/2024 and GP/ST/No.49/2024 (all Pind. 1/2026).

EECA Watch · free

Get new pieces in your inbox.